Geodesic Dome Home

Week 58 - ALL DONE :-D

New Triangular Storage Room

Week 51 Saturday September 1st, 2007

New Homes are finished :-D

Week 50 - Saturday 25th August 2007

    The Square House is 99% finished and we will move into it next week.  I will take comprehensive pictures and post them next week. 

Then Poom will start a new project to build a storage shack and an extra shower room on the deck.

Week 44 - Friday the 13th (July 2007)

Moving into the Dome at last :-D

Week 43 - 7 July 2007

Week 42 - 30 June 2007

Week 41 - 23 June 2007

Week 39 - 9 June 2007

Week 38-2 - 3 June 2007

Week 38-1 - 2 June 2007

Week 36 - 20 May 2007

Second Floor - Bedroom Area View from second floor
Additional Support for 2nd floor At the rear entrance

Week 34 - 7 May 2007

Stripping old paint  

Week 33 - 28 April 2007

Shingles are being installed  
Second floor and the grand stairs  

Week 32 - 21 April 2007

Week 30 - 11 April 2007

Week 29/3 - 7 April 2007

Week 29/2 - 6 April 2007

Week 29/1 - 5 April 2007

Week 28/7 - 31 March 2007

Week 28/6 - 30 March 2007

Week 28/5 - 29 March 2007

Week 28/4 - 28 March 2007

Week 28/3 - 27 March 2007

Week 28/2 - 26 March 2007

Week 28/1 - 25 March 2007

The Team Trying to find the CENTER !!!

Week 27 - 24 March 2007

Dome Materials arrived from Australia

Week 26 - 17 March 2007

Week 25 - 10 March 2007

Week 23 - 24 Feb 2007

Week 19 - 27 Jan 2007

Week 18 - 20 Jan 2007

Week 17 - 13 Jan 2007

Week 16 - 6 Jan 2007 - Start of the New Year

Site for one of the two septic tanks Dome Home Entrance Extension
Site of the Sala Northern deck

Week 15 - 30 Dec 2006 @ New Year's break

Week 14 - 16 Dec 2006

Week 13 - 10 Dec 2006

This is where the bathroom is.  Concrete floor.

Week 12 - back to the future :-( - 2 Dec 2006

After a long break, we finally got started again.

Week 4 - 7 Oct 2006

Not much progress this week because of the torrential rains earlier in the week and the End of Buddhist Lent holiday.

Lounge Well Area Splitting the railroad tires
One railroad tire produces 5 usable boards (1.35 sq.m total) 15 cm wide, 4 cm thick, and 1.9 meters long
From one railroad tire Electric planar
After it has gone through the planar Teak floor boards for interior from Si Phraya Home
Slotted boards for nail-free installation  

Week 3 - 1 Oct 2006

Slower progress last week because it rained 3 out of 5 days (1/10/2006) But still, all the bearings for the deck are finished
39 bearings, deck is expanded to 755 sq.meters!! Started working on the lounge well

Week 2 - 23 Sept 2006

23 Sept 2006 Many bearings are already up (23/9/06)
Bearing in the southeast corner is about 30 cm high (23/9/06) The north bearings are about 120 cm high (23/9/06)
Before casing and cementing (23/9/06) Footing (23/9/06)

Week 1 - 16 Sept 2006

16 Sept 2006 Morning 16 Sept 2006 Afternoon