Geodesic Dome Home
Week 58 - ALL DONE :-D
New Triangular Storage Room
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Week 51 Saturday September 1st, 2007
New Homes are finished :-D
Week 50 - Saturday 25th August 2007
The Square House is 99% finished and we will move into it next week. I will take comprehensive pictures and post them next week.
Then Poom will start a new project to build a storage shack and an extra shower room on the deck.
Week 44 - Friday the 13th (July 2007)
Moving into the Dome at last :-D
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Week 43 - 7 July 2007
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
|
|
|
|
|
|
|
|
![]() |
![]() |
![]() |
![]() |
Week 42 - 30 June 2007
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Week 41 - 23 June 2007
|
|
|
|
|
|
|
|
|
Week 39 - 9 June 2007
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Week 38-2 - 3 June 2007
|
|
|
Week 38-1 - 2 June 2007
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Week 36 - 20 May 2007
|
|
|
|
|
|
|
|
|
| Second Floor - Bedroom Area | View from second floor |
|
|
|
| Additional Support for 2nd floor | At the rear entrance |
Week 34 - 7 May 2007
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Stripping old paint |
Week 33 - 28 April 2007
|
|
|
|
|
|
|
|
|
| Shingles are being installed | |
|
|
|
|
|
|
|
|
|
| Second floor and the grand stairs |
Week 32 - 21 April 2007
|
|
|
|
|
|
|
|
|
|
|
|
Week 30 - 11 April 2007
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Week 29/3 - 7 April 2007
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Week 29/2 - 6 April 2007
|
|
|
|
|
|
Week 29/1 - 5 April 2007
|
|
|
|
|
|
|
|
|
Week 28/7 - 31 March 2007
|
|
|
|
|
|
Week 28/6 - 30 March 2007
|
|
|
|
|
|
|
|
|
Week 28/5 - 29 March 2007
|
|
|
|
|
|
|
|
|
Week 28/4 - 28 March 2007
|
|
|
|
|
|
|
|
|
Week 28/3 - 27 March 2007
|
|
|
|
|
|
|
|
|
Week 28/2 - 26 March 2007
|
|
|
|
|
|
|
|
|
Week 28/1 - 25 March 2007
|
|
|
| The Team | Trying to find the CENTER !!! |
|
|
|
|
|
|
|
|
|
|
|
|
Week 27 - 24 March 2007
|
|
|
|
|
|
|
|
|
| Dome Materials | arrived from Australia |
Week 26 - 17 March 2007
|
|
|
|
|
|
|
|
|
Week 25 - 10 March 2007
|
|
|
|
|
|
|
|
|
Week 23 - 24 Feb 2007
|
|
|
|
|
|
|
|
|
Week 19 - 27 Jan 2007
|
|
|
|
|
|
Week 18 - 20 Jan 2007
|
|
|
|
|
|
|
|
|
Week 17 - 13 Jan 2007
|
|
|
|
|
|
Week 16 - 6 Jan 2007 - Start of the New Year
|
|
|
| Site for one of the two septic tanks | Dome Home Entrance Extension |
|
|
|
| Site of the Sala | Northern deck |
Week 15 - 30 Dec 2006 @ New Year's break
Week 14 - 16 Dec 2006
|
|
|
|
|
|
|
|
|
Week 13 - 10 Dec 2006
This is where the bathroom is. Concrete floor.
|
|
|
|
|
|
|
|
|
Week 12 - back to the future :-( - 2 Dec 2006
After a long break, we finally got started again.
|
|
|
Week 4 - 7 Oct 2006
Not much progress this week because of the torrential rains earlier in the week and the End of Buddhist Lent holiday.
|
|
|
| Lounge Well Area | Splitting the railroad tires |
|
|
|
| One railroad tire produces 5 usable boards (1.35 sq.m total) | 15 cm wide, 4 cm thick, and 1.9 meters long |
|
|
|
| From one railroad tire | Electric planar |
|
|
|
| After it has gone through the planar | Teak floor boards for interior from Si Phraya Home |
|
|
|
| Slotted boards for nail-free installation |
Week 3 - 1 Oct 2006
|
|
|
| Slower progress last week because it rained 3 out of 5 days (1/10/2006) | But still, all the bearings for the deck are finished |
|
|
|
| 39 bearings, deck is expanded to 755 sq.meters!! | Started working on the lounge well |
Week 2 - 23 Sept 2006
|
|
|
| 23 Sept 2006 | Many bearings are already up (23/9/06) |
|
|
|
| Bearing in the southeast corner is about 30 cm high (23/9/06) | The north bearings are about 120 cm high (23/9/06) |
|
|
|
| Before casing and cementing (23/9/06) | Footing (23/9/06) |
Week 1 - 16 Sept 2006
|
|
|
| 16 Sept 2006 Morning | 16 Sept 2006 Afternoon |